Group update

Council refuses Bellville Solar Farm near Monivea

Galway County Council has refused the nearby 239-hectare proposal on eleven grounds. The decision can be appealed.

· Updated 1 October 2026

Galway County Council refused planning permission for the Bellville Solar Farm near Monivea and Abbeyknockmoy on 30 September 2026. The applicant is Heron Solar Ltd., and the planning reference is 26/61362.

The application, received on 7 August, covered 239 hectares across fourteen townlands. It sought a ten-year planning permission for more than one million square metres of ground-mounted solar panels, 32 medium-voltage stations, access tracks, underground cabling and associated works. The proposed operating lifetime was 40 years.

The Council’s decision sets out eleven reasons for refusal, finding the proposal contrary to policies in the Galway County Development Plan 2022–2028.

RTÉ reported that more than 350 submissions were made on the application. Galway Bay FM reported relief and elation among local residents following the decision.

AMASS — Abbeyknockmoy and Monivea Against Solar Sprawl — is the neighbouring community group campaigning on this development. It brings together residents and families from those areas and the surrounding townlands. Its refusal announcement, website and Facebook page are linked below for anyone who wants to follow their work.

An appeal remains possible. The applicant can appeal the refusal to An Coimisiún Pleanála within four weeks beginning on the date of the Council’s decision.

Bellville and Blackthorn are separate planning applications with different sites, documents and circumstances. The reasons below are findings about Bellville. They should not be assumed to apply to Blackthorn, and the Bellville decision does not determine Blackthorn’s outcome.

The eleven reasons for refusing Bellville

This is a plain-language summary of the Council’s refusal schedule for application 26/61362. Each reason concerns the Bellville proposal. Read the original decision for the full wording and policy references.

  1. Overall project and grid connection. The Council cited inconsistent technical assessments, insufficient justification for the location under its renewable-energy strategy, and uncertainty about the future substation and grid connection. It considered the proposal premature.
  2. Land interests and consents. The Council was not satisfied that the applicant had adequately demonstrated the necessary legal interest in the land or the relevant owners’ approval.
  3. Lough Corrib Special Area of Conservation. The information supplied did not satisfy the Council that adverse effects on the integrity of Lough Corrib SAC could be excluded in light of its conservation objectives.
  4. Environmental-impact screening. The Council found deficiencies and inconsistencies in the screening information and assessment of the overall project. It lacked adequate information to make a robust determination about likely significant environmental effects.
  5. Road space and future services. The Council considered that grid-connection works would restrict future road works, drainage upgrades, water mains and other services within public roads.
  6. Flood risk. The site’s flood-zone location and missing design detail left the Council unsatisfied about flooding on the site or the risk of causing or worsening flooding elsewhere.
  7. Overhead electricity lines. The Council found insufficient evidence of consultation with ESB/EirGrid and inadequate demonstration of overhead-line locations and required clearances from panels.
  8. Public water infrastructure. Following Uisce Éireann’s submission, the Council identified potential construction over existing infrastructure and failure to meet required separation distances.
  9. Traffic and road safety. The Council raised concerns about the suitability of local roads for additional heavy vehicles, access arrangements, manoeuvring and possible conflicts affecting road users’ safety.
  10. Glint and glare. The Council considered that the assessment had not adequately addressed effects on road users, including national-road requirements.
  11. Archaeology. Following the Department of Housing, Local Government and Heritage’s submission, the Council considered the archaeological assessment deficient and incomplete against the relevant protection requirements.
← All updates